In 2018, Figener participated in an executive project to install a 138/13.8 kV substation.
The substation was built in 2018 and has 2 transformers of 12 MVA each.
For the project, FIGENER performed the following activities:
- Power Flow Study
- Short Circuit Study
- Protection and Selectivity Coordination Study
- 138/13.8 kV Substation Executive Project:
- Civil, including Control and Protection Room
- Electromechanical
- Electric
- Telecommunications
- Executive Project of Compact Overhead Network 13.8 kV from SE to the factory
- Technical Analysis of Suppliers
The substation project was prepared with the help of CAE Primtech, a modern BIM tool developed especially for substation projects.