FIGENER participates in Biomass Boiler Interconnection Project
Figener carries out the executive project for the interconnection of a 200 t/h Biomass boiler.
Figener carries out the executive project for the interconnection of a 200 t/h Biomass boiler.
Over the past few years, FIGENER has participated in several improvement projects for Motor Thermoelectric Plants.
In 2018, Figener participated in an executive project to install a 138 / 13.8 kV substation. The substation was built in 2018 and has 2 transformers of 12 MVA each. For the project, FIGENER carried out the following activities: Power Flow Study Short Circuit Study Protection and Selectivity Coordination Study.